Major operations requiring engine removal
The following work can only be carried out after removal of the engine from the car: a) Crankshaft main bearings - renewal.
b) Crankshaft - removal and refitting.
c) Flywheel - removal and refitting.
d) Crankshaft rear oil seal - renewal.
e) Oil pump - removal and refitting.
See also:
Idle speed control valve - removal and refitting
Note: A new gasket must be used when
refitting the valve.
2.0 litre SOHC models
1 Disconnect the battery negative lead.
2 Disconnect the idle speed control valve
wiring plug by releasing the reta ...
Electrical fault-finding - general information
Note: Refer to the precautions given in “Safety
first!” and in Section 1 of this Chapter before
starting work. The following tests relate to testing
of the main electrical circuits, and should not ...
Heater matrix - removal and refitting
Removal
1 With the heater removed from the vehicle
as previously described, extract the two
securing screws and slide the matrix out of
the heater casing.
2 If further dismantling is necessary, c ...